An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. Apportioned effort is one of three earned value management (EVM) types of activities used to measure work performance.
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.
A formally charted group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating such decisions.
A component of the project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated.
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
An activity that can be planned and measured and that yields a specific output. Discrete effort is one of three earned value management (EVM) types of activities used to measure work performance.
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the dta date, and schedule constraints.
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints.
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
A critical path method technique for calculating the early start and elarly finish dates by working forward through the schedule model from the project start date or a given point in time.
A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.
A component of the project or program management plan that describes how the roles and responsibilities, reporting relationships, and staff management will be addressed and structured.
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints.
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.
An activity that does not produce definitive end products and is measured by the passage of time. The level of effort is one of three earned value management (EVM) types of activities used to measure work performance.
A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities.
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program.
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
A group of related projects, subprograms, and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
The application of knowledge, skills, tools, and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
A management structure that standardizes the program-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
A condition or capability that is required to be present in a product, service, or result to satisfy a contract or other formally imposed specification.
A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
A component of the project or program management plan that establishes the activities for developing, monitoring, and controlling the project or program.
A representation of the plan for executing the project's activities, including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts.
The approved version of a scope statement, work breakdown structure (WBS) and its associated WBS dictionary, which can be changed only through formal change control procedure and is used as a basic for comparison.
An individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio.
A technique used to estimate cost or duration by applying an average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion (BAC) and the estimate at completion (EAC).
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.